The full upgrade schedule is posted below. We will be upgrading by building and floor. Please review the red highlight below, so that the upgrade goes smoothly for you.

Read this first

  1. Make sure you have not saved anything to your desktop or have any personal data on the computer that isn't in My Documents or department shared drives. (Details)
  2. Confirm that you are logged out of your computer account on the Kickoff Date
  3. Do not switch off your computer on the Kickoff Date

Building/Floor

Kickoff Date (overnight)

Computer Ready for use

Status

Sawyer 4th FloorAugust 5th at 6PMAugust 6(tick) Completed
Sawyer 6th FloorAugust 5th at 6PMAugust 6(tick) Completed
Sawyer 8th FloorAugust 7th at 6PMAugust 8(tick) Completed
Sawyer 9th FloorAugust 7th at 6PMAugust 8(tick) Completed
Sawyer 10th FloorAugust 7th at 6PMAugust 8(tick) Completed
73 Tremont 7th FloorAugust 9th at 6PMAugust 12(tick) Completed
73 Tremont 12th FloorAugust 9th at 6PM (Originally scheduled for Aug 13th)August 12(tick) Completed
Laptop UsersAugust 26th to August 30th (thumbs up) In Progress
Sawyer ClassroomsAugust 23rd (tick) Completed
Graduate Student LoungeAugust 16th (tick) Completed
Sawyer 5th Floor Computer ClassroomsAugust 16th and 23rd (tick) Completed
Sawyer Computing CenterAugust 26th (thumbs up) In Progress
Trading Room & Financial CenterAugust 16th (tick) Completed